Ongoing Projects

1200 Family Flats Regi Lalma Peshawar (Phase - I)

Date of Approval by GB: 108th GB, Dec 20, 2012
Tender Cost: 3236.810
Progressive Expenditure upto June 30, 2021: 3109.02
Financial Progress: 96%
Approved PC-I Cost: 2817.410
Date of Start / Completion (Extended): Apr 19, 2011 / Jul 30, 2021
Physical Progress: 97%

Labour City (856 F.F) at Regi Lalma Peshawar Phase - I (Package-II)

Date of Approval by GB: 121th GB, Feb 27, 2013
Tender Cost: 2204.66
Progressive Expenditure upto June 30, 2021: 1989.06 1989.06
Financial Progress: 91%
Approved PC-I Cost: 2276.200
Date of Start / Completion (Extended): Nov 11, 2013 / Jul 30, 2021
Physical Progress: 95%

WWB KP Office Building at Hayatabad, Peshawar (Civil & Allied Building Works)

Date of Approval by GB: 99th / 137th GB, Oct 09, 2008 / Mar 30, 2017
Tender Cost: 530.00
Progressive Expenditure upto June 30, 2021: 534.229
Financial Progress: 95%
Approved PC-I Cost: 530.00
Date of Start / Completion (Extended): Mar 18, 2019 / Jun 30, 2021
Physical Progress: 98%

Working Folks Grammar School Male/Female at Shahbaz Azmat Khel Bannu

Date of Approval by GB: 138th GB, Sep 13, 2017
Tender Cost: 241.843
Progressive Expenditure upto June 30, 2021: 168.599
Financial Progress: 70%
Approved PC-I Cost: 219.92
Date of Start / Completion (Extended): Jan 08, 2018 / Jun 30, 2021
Physical Progress: 75%