1200 Family Flats Regi Lalma Peshawar (Phase - I)
|
| Date of Approval by GB: |
108th GB, Dec 20, 2012 |
| Tender Cost: |
3236.810 |
| Progressive Expenditure upto June 30, 2021: |
3109.02 |
| Financial Progress: |
96% |
| Approved PC-I Cost: |
2817.410 |
| Date of Start / Completion (Extended): |
Apr 19, 2011 / Jul 30, 2021 |
| Physical Progress: |
97% |
Labour City (856 F.F) at Regi Lalma Peshawar Phase - I (Package-II)
|
| Date of Approval by GB: |
121th GB, Feb 27, 2013 |
| Tender Cost: |
2204.66 |
| Progressive Expenditure upto June 30, 2021: 1989.06 |
1989.06 |
| Financial Progress: |
91% |
| Approved PC-I Cost: |
2276.200 |
| Date of Start / Completion (Extended): |
Nov 11, 2013 / Jul 30, 2021 |
| Physical Progress: |
95% |
WWB KP Office Building at Hayatabad, Peshawar (Civil & Allied Building Works)
|
| Date of Approval by GB: |
99th / 137th GB, Oct 09, 2008 / Mar 30, 2017 |
| Tender Cost: |
530.00 |
| Progressive Expenditure upto June 30, 2021: |
534.229 |
| Financial Progress: |
95% |
| Approved PC-I Cost: |
530.00 |
| Date of Start / Completion (Extended): |
Mar 18, 2019 / Jun 30, 2021 |
| Physical Progress: |
98% |
Working Folks Grammar School Male/Female at Shahbaz Azmat Khel Bannu
|
| Date of Approval by GB: |
138th GB, Sep 13, 2017 |
| Tender Cost: |
241.843 |
| Progressive Expenditure upto June 30, 2021: |
168.599 |
| Financial Progress: |
70% |
| Approved PC-I Cost: |
219.92 |
| Date of Start / Completion (Extended): |
Jan 08, 2018 / Jun 30, 2021 |
| Physical Progress: |
75% |
|